Feb 26,  · Inactive Tasks in MS PROJECT Posted on February 26, by Nenad Trajkovski. Hi, this Post will be a really short one! I’m going to explain how Inactive Task is different in MS PROJECT First, notice that this functionality is available only with MS PROJECT PROFESSIONAL version. I’ll create new Project,first:Estimated Reading Time: 3 mins. Nov 01,  · (This accounts for the 3 day task that was inactivated) Now in Microsoft Project once you inactivate a task it will automatically inherit the predecessor of the inactive task and schedule the remaining tasks accordingly. Figure 4: Project Schedule () prior to setting Task 2 to inactive. All of the tasks are active and linked ted Reading Time: 2 mins. This feature is only available in Project Professional. Click View, and then in the Task Views group, click Gantt Chart. In the table, select the number of the task you want to inactivate. Click Task, and then in the Schedule group, click Inactivate. The inactive task stays in the task list, but the text is grayed out and has a line through it.
 
 

Microsoft project 2013 inactive task free download.Inactivate a task

Microsoft Project Microsoft Project is the dominant project management software at most companies for a reason: Project offers a comprehensive set of project management tools, and has for years. The latest version of Project is all that and more, allowing deployment both on-site and in the cloud. With the new cloud deployment feature. Nov 01,  · (This accounts for the 3 day task that was inactivated) Now in Microsoft Project once you inactivate a task it will automatically inherit the predecessor of the inactive task and schedule the remaining tasks accordingly. Figure 4: Project Schedule () prior to setting Task 2 to inactive. All of the tasks are active and linked ted Reading Time: 2 mins. Nov 15,  · Following last month’s announcement: The New Microsoft Project reaches RTM!, you can now download the following trials for the following languages: Arabic, English, Chinese (Simplified), Chinese (Traditional), Dutch, French, German, Hebrew, Italian, Japanese, Korean, Portugese (Brazil), Russian, Spanish: Microsoft Project Professional
 
 
 
 

With the Active field, you can inactivate tasks to remove them from the Project plan. Inactive tasks remain available for use in a later phase, a later project, or for reporting or historical purposes. Inactive tasks no longer affect other tasks or the overall Project plan. Unlike deleted tasks, inactive tasks are recoverable and can be returned to active status if needed. Reactivated tasks retain any dependencies, constraints, or resource assignments associated with them.

You can create reports of inactivated tasks. Microsoft Project retains baseline information for inactivated tasks. Entry Type Entered. Best Uses The Active field is useful when various proposals are being presented for a Project plan and ultimately one course of action will be selected. The Active field is also useful when a task or set of tasks is being cut because of a scaling back of project scope.

With the Active field, you can experiment with inactivating and reactivating tasks to see the resulting schedule effects. Only the active tasks are considered part of the Project plan, but a record of the inactive tasks and their properties still exist for historical purposes, or for reactivation into the Project plan at a later time. Example Your team is planning the development of a new product that has a long list of features represented in the Project plan. After estimating feature costs, examining priorities, and reviewing the desired date to market, you know you need to make feature cuts.

You add the Active field to a task sheet, and select No for the features being proposed for cuts. When you remove those features, the schedule and costs are adjusted in the Project plan. At the next status meeting, you present a report listing the inactivated items. If a stakeholder insists that a certain feature be returned to the project, you reactivate the tasks associated with that feature.

Remarks Another way to inactivate or reactivate a selected task is to click the Task tab, and then in the Tasks group, click Inactivate. Inactive tasks appear dimmed with a strikethrough. You can easily hide inactive tasks by filtering them out. On the View tab, in the Data group, click the arrow next to Filter , and then click Active. A subscription to make the most of your time. Try one month free. Need more help? Expand your Office skills.

Get new features first. Was this information helpful? Yes No. Any other feedback? The more you tell us, the more we can help. How can we improve? Send No thanks.